We have been asked to share the following information provided by Cambridgeshire Highways –
“This is a general notification that we are due to start a number of large-scale maintenance schemes. This will involve the carriageway resurfacing of large sections of highway in various parishes. These works will be done under a road closure with diversion routes in place. The roads will be closed to all traffic, with the exception of access to residents and businesses within the closure itself.
The current programme of works is as follows:
- Fenland Way – Chatteris: From 07/08/23 to 08/09/23 (Night works between 21:00 – 06:00)
- New Road – Warboys: From 11/09/23 to 20/10/23 (Night works between 21:00 – 06:00)
- Milton Interchange – Milton: From 23/10/23 to 07/12/23 (Night works between 21:00 – 06:00)
- Bates Drove – Littleport: From 04/03/24 to 26/04/23 (Day works between 08:00 and 17:00). Unlike the previous 3 schemes; this closure will be 24/7 and not just within the working hours.
Please note that both the works programme and diversion routes may change, but we [Cambridgeshire Highways] will contact you again closer to the start dates to provide an accurate update.
Letter drops will go out to nearby properties 1 month in advance of the works.”